Resources
Overview of project team, timeline, and links to all resource allocation docs.
Allocate by share of capacity
Use this when you want to book a member as a percentage of their contracted time (for example 50% of capacity for two weeks).- Open the allocation dialog from a task Allocations row, Members → Resource allocation, or a project Resources timeline block.
- Pick the member and set the allocation period.
- Select the % toggle above the amount field.
- Enter the share of capacity. Pike converts to total hours using the member’s employment contract for those dates.
- Review the summary line at the bottom of the dialog (hours per day, per week, and share of capacity). Save.
Allocation properties
All three hour modes and how they convert.
Placeholder positions: assign, allocate, convert
Use a position when you know the role (for example “Senior consultant”) but not yet the person.1. Define the position
Under Members → Settings → Member positions, create the role and its default hourly rate.2. Assign the position on the task
On the task page or sidebar, open Assigned to and pick the position from the same picker as members. The position appears on the task with a position icon. You can also add positions when building the project team on the Resources tab.3. Allocate hours to the placeholder
Expand Allocations on the task (or open the position row on Members → Resource allocation → Timeline). Click + on the position row and enter dates and hours. Use h or the calendar (per-weekday) toggle. % is not available for positions.4. Convert to a member when someone is hired
When you are ready to staff the role, click Assign on the position row in Allocations (or use the assignment picker). Choose the member.- With no allocations yet, Pike replaces the position assignee immediately.
- With existing allocation blocks, Pike asks you to confirm; the planned hours move to the member.
Members
Member positions and skills under Members → Settings.
Task page and sidebar
Open a task from a board, list, timeline, or sidebar. On the full task page or in the task sidebar, expand Allocations below the description. The section lists each assignee (member or position) with allocation blocks, total hours, and date ranges. Use + on a row to add a block, or Allocate assignee to pick someone new. Pike adds them to the task when needed. Allocations appear only when the task belongs to a project.Edit tasks
Task page, sidebar, and assignment pickers.
Project resources
Go to the project Resources tab to add members and positions, then create allocations on the timeline heatmap. The view reflects each person’s load across the whole workspace, not just this project. Expanded member rows show assigned tasks; drag allocation bars to adjust dates. Position rows appear on the workspace timeline the same way.Resources
Adding members, rates, and the project timeline.
Workspace resource allocation
Open Members → Resource allocation for workspace-wide planning.- Chart: capacity heatmap and summary charts; use the gear menu to switch weeks vs months, show remaining capacity, and display hours or percentages. Heatmap cells stack confirmed (solid) and proposed (hatch) hours unless you filter to one side.
- Timeline: member and position rows with draggable blocks; click a block to edit. The utilization row under each member uses the same stacked fill.
Workspace capacity
How available and allocated hours are calculated.