Full-time equivalent (FTE)
Full-time equivalent (FTE) is a unit that converts the hours worked by any mix of full-time, part-time, and contractor staff into a single number comparable to one standard full-time role.
How to calculate FTE
Divide the hours a person actually works by the hours that count as a standard full-time week at the firm, usually 40. Someone working 20 hours a week against a 40-hour standard is 0.5 FTE. Add up everyone on a team and the total gives capacity in full-time units, regardless of how the underlying contracts are structured.
FTE = Hours worked / Standard full-time hours
Example: a part-timer working 20 hours against a 40-hour standard week is 0.5 FTE.
Why use FTE instead of headcount
Headcount counts people. FTE counts capacity. A team of 10 people could be 10 FTE, or it could be 6 FTE if half of them work part-time or split their week across client accounts. Budgeting and staffing plans built on headcount alone overstate capacity the moment the team includes anyone who is not full-time.
This matters most where contractors, interns, or part-time specialists sit alongside full-time staff. Converting everyone to the same FTE unit is what makes a staffing plan or a utilization target comparable across a mixed team.
FTE vs bench time and utilization rate
FTE, bench time, and utilization rate all touch capacity, but they answer different questions. FTE answers how much staffing capacity exists in the first place, before any of it gets allocated to work. Bench time and utilization rate describe what happens to that capacity once people are on the clock: how much of it sits unassigned, and how much of it bills.
A resourcing plan typically starts with FTE (how many standard full-time roles worth of people do we have), then tracks allocation, bench time, and utilization against that baseline.
Example
A studio has 8 full-time employees at 40 hours a week, 3 part-time designers at 20 hours a week, and 2 contractors billing 10 hours a week each. Full-time staff contribute 8 FTE. The part-timers contribute 3 x (20/40) = 1.5 FTE. The contractors contribute 2 x (10/40) = 0.5 FTE. Total staffing capacity is 10 FTE, built from 13 actual people.