Level of effort (LOE)
Level of effort (LOE) is an estimate of the hours or work a task, deliverable or project will need from your team. Agencies and consultancies base quotes, budgets and staffing plans on it. An LOE that is too low shows up later as overruns, write-offs and overloaded people.
The two meanings of level of effort
In agency and consulting work, LOE usually means an effort estimate: the hours a piece of work will take, broken down by role. A scoping document might list an LOE for each line item, such as 24 hours for discovery workshops.
In earned value management (EVM), level of effort is also an activity type. LOE activities are support work with no discrete output of their own, such as project management, client coordination or ongoing QA support. Their earned value follows elapsed time: when the project is halfway through its schedule, the LOE activity has earned half its budget.
Because LOE earned value follows the calendar, LOE activities always show a schedule variance of zero. Keep them small in an EVM baseline. Large LOE activities make overall schedule performance look healthier than the discrete work alone.
How to estimate level of effort
Break the work down until each item is small enough for the person doing it to estimate with confidence, usually a few hours to a few days. Estimate per role, since a senior strategist hour and a junior designer hour have different costs and rates.
For uncertain tasks, a three-point estimate gives a better LOE than a single guess. Ask for an optimistic, a most likely and a pessimistic figure, then weight them.
Check every estimate against history. Planned vs actual hours from similar past projects are the best test of a new LOE.
Three-point LOE = (Optimistic + 4 × Most likely + Pessimistic) / 6
Example: a developer estimates an integration at 16 hours if all goes well, 24 hours most likely and 44 hours if the client's API is poorly documented. LOE = (16 + 4 × 24 + 44) / 6 = 156 / 6 = 26 hours.
How agencies use LOE for scoping and quoting
LOE by role multiplied by each role's rate is the price for time-and-materials work and the cost floor for a fixed fee. Multiply the same hours by internal cost rates to see the margin before you send the quote.
The LOE also becomes the time budget for delivery. Load it into the project plan as hours per role and track logged hours against it. A project that has used 60% of its LOE at 40% complete is burning hours faster than planned.
For retainers and managed services, LOE is often the unit of the contract. A support retainer might include, for example, 40 hours a month, with a set rate for hours above it.
Common LOE mistakes
Estimating only production time. Meetings, reviews, revision rounds, client feedback and project management take real hours. Leave them out and the LOE is low on every project.
Letting sales estimate alone. The people who will deliver the work should estimate it, or at least review the estimate before it reaches the client.
Padding every task. Add contingency as one visible line, where your team can see it and the client can discuss it.
Never revisiting the LOE. When scope changes, update the LOE through change control and reprice the work.
Example
Example: an agency scopes a website redesign. The LOE by role is strategy 20 hours, UX 60 hours, design 90 hours, development 160 hours, QA 30 hours and project management 45 hours, for 405 hours in total. At example rates of $160 for strategy, $130 for UX and design, $120 for development and QA, and $110 for project management, the quote is $50,450, plus a visible 10% contingency of $5,045. Halfway through delivery, with 50% of deliverables approved, the team has logged 240 hours: 37.5 hours more than half the LOE, and the point to review scope with the client.