Earned value management (EVM)

Earned value management (EVM) is a method for measuring project performance by comparing the value of completed work with planned work and actual cost. On fixed-fee client work, it turns logged hours and a percent complete estimate into an early read on whether the project will finish inside its fee. Budget burn measures how much of the fee your team has used. EVM also measures how much finished work that spend represents.

The three measures: planned value, earned value and actual cost

EVM starts from the budget at completion (BAC): the total budget for the work, in money or hours. Every other measure is a share of that number, which makes projects of different sizes comparable.

Planned value (PV) is the budget for the work scheduled to be done by today. Earned value (EV) is the budget for the work actually done by today. Actual cost (AC) is what that work cost: for a services firm, the hours logged to date, or those hours valued at a rate.

PV and EV come from the same budget. The only difference is the percent complete applied to it: planned progress for PV, actual progress for EV.

PV = Planned % complete × BAC; EV = Actual % complete × BAC; AC = Actual hours or cost to date

Example: on a $60,000 project planned to be 50% done by week 6 but actually 40% done, PV is $30,000 and EV is $24,000.

Cost variance (CV)

Cost variance is the gap between the budgeted value of the work your team has delivered and what it cost to deliver. On a fixed-fee project, it is the EVM measure closest to margin.

A positive CV means the work done cost less than its budget. A negative CV means your team spent more than the completed work was worth. Zero means delivery is exactly on budget for the progress made.

CV = EV - AC

Example: an EV of $24,000 and an AC of $31,500 give a CV of -$7,500. Your team has spent $7,500 more than the budget for the work done to date.

Schedule variance (SV)

Schedule variance compares the work done with the work planned by the same date. It measures whether delivery is ahead of or behind plan, expressed in money or hours rather than days.

A positive SV means the project is ahead of schedule, and a negative SV means it is behind. A negative SV with a CV near zero often means work is waiting on the client, for example for feedback or content. A negative CV means the work done has cost more than planned, whatever the cause.

SV = EV - PV

Example: an EV of $24,000 against a PV of $30,000 gives an SV of -$6,000, which is 20% short of the planned progress for week 6.

How agencies and consultancies apply EVM to fixed-fee projects

Most services firms already have two of the three inputs. The fee or hour budget gives BAC and, phased by week or milestone, gives PV. Timesheets give AC. The missing input is percent complete, which your project lead estimates at each review, ideally from finished deliverables or milestones.

Use one basis throughout. If the budget is in hours, measure AC in logged hours. If the budget is the fee, value logged hours at the rate used to build the estimate. Comparing a fee-based BAC with AC at internal cost rates produces a variance that mostly reflects margin rather than delivery.

Pike tracks hours against project budgets live, in total or per phase, which keeps AC current between reviews. Your team adds the percent complete estimate to calculate EV.

Common mistakes with earned value

Reading percent complete from hours spent. If 50% of the budget is used and the project is called 50% complete, EV equals AC and CV is always zero. Estimate progress from finished work instead.

Rewriting the baseline after every change. Approved change orders add to BAC. Unapproved scope creep should stay in the numbers as a negative CV.

Working from late timesheets. AC is only as current as the hours logged, and missing time makes CV look better than it is.

Reviewing once a month. On a 12-week project, a monthly review gives your team two chances to act before handover. A weekly review gives eleven.

Example

For example, a 12-week fixed-fee website project has a $60,000 budget, built as 400 hours at a $150 blended rate. The project plan has 50% of the work done by the end of week 6, a PV of $30,000. At the week 6 review, the project lead estimates the work at 40% complete, an EV of $24,000. The team has logged 210 hours, an AC of $31,500. CV is $24,000 - $31,500 = -$7,500 and SV is $24,000 - $30,000 = -$6,000. The project is behind schedule and over cost for the progress made. If the team continues at the same cost efficiency, the estimate at completion is $60,000 / ($24,000 / $31,500) = $78,750, or $18,750 over the fee.

Related terms

  • Earned value (EV)
  • Actual cost (AC)
  • Cost variance (CV)
  • Cost performance index (CPI)
  • Estimate at completion (EAC)
  • Budget burn rate

FAQ

Your business runs better on Pike.

Contact sales
  • ISO 27001 CertifiedISO 27001
  • GDPR CompliantGDPR
  • AICPA SOC 2 Type IISOC 2 Type II

Built to keep sensitive client data secure and private.

Pike box logoPike
Features
ProjectsResourcing & capacityFinance & invoicingDashboardsCustomers & salesTime & absencePike MCPIntegrations
Company
EnterpriseBlogOur storySwitch playbookMigration guideGet in touch
Industries
Creative agenciesMarketing agenciesDigital agenciesConsulting firmsIT consultanciesArchitecture firms
Resources
DocsChangelogPrivacy policyTerms and conditionsGlossaryFree toolsFAQ
All systems operational

Engineered around the 🌎

© 2026 Pike. All rights reserved.