Cost performance index (CPI)

Cost performance index (CPI) is an earned value ratio that measures how much budgeted work your team completes for each unit of actual cost. On a fixed-fee project, a CPI below 1 means each logged hour covers less than an hour of budgeted work, and margin falls for as long as the ratio remains below 1.

How to calculate CPI

Divide earned value by actual cost. Earned value is the budget for the work completed to date: percent complete multiplied by the total budget. Actual cost is what that work has cost, from timesheets valued at the rate used in the budget, or hours logged if the budget is in hours.

CPI is a ratio, which makes it comparable across projects of different sizes. A CPI of 0.85 on a $20,000 project and on a $200,000 project describe the same cost efficiency.

CPI = EV / AC

Example: a project with an EV of 180 hours and 225 hours logged has a CPI of 180 / 225 = 0.80.

How to read CPI above and below 1

A CPI of 1 means the work done cost exactly what was budgeted for it. Above 1, the project is under cost: a CPI of 1.10 means each $1 spent completed $1.10 of budgeted work. Below 1, the project is over cost: a CPI of 0.80 means each $1 spent completed $0.80 of budgeted work.

On a fixed-fee project, a CPI below 1 is margin leaving the project. On time and materials work the client pays for the extra hours, but a low CPI still means the estimate was low, and a client with a budget cap will notice.

CPI also gives the simplest forecast of final cost. If performance continues at the current CPI, the estimate at completion is the budget divided by CPI.

EAC = BAC / CPI

Example: a 300-hour budget with a CPI of 0.80 gives an estimate at completion of 300 / 0.80 = 375 hours, 75 hours over budget.

CPI vs SPI

Schedule performance index (SPI) is the matching schedule ratio: earned value divided by planned value. CPI measures cost efficiency. SPI measures progress against the plan.

Read them together. A low SPI with a CPI near 1 often means work is waiting, for example on client feedback, while your team is efficient on the work it does. A low CPI with an SPI near 1 means your team is keeping pace by spending more hours than planned. Both below 1 is the case to escalate first.

SPI = EV / PV

Example: an EV of 180 hours against a PV of 210 hours gives an SPI of 180 / 210 = 0.86.

How agencies and consultancies use CPI

Project leads calculate CPI at each weekly or milestone review on fixed-fee work and compare it across the portfolio. A list of live projects sorted by CPI shows which client projects are losing margin this week, before the month-end numbers arrive.

CPI by service line is also an estimating input. If brand projects close with a CPI below 1 quarter after quarter, the estimates for that work are low, and your team should price the next one with more hours or a higher fee.

Pike tracks hours against project budgets live, which keeps the AC side of CPI current. Your project lead supplies the percent complete estimate for EV.

Common mistakes with CPI

Using hours spent as percent complete. That makes EV equal to AC and CPI always 1.

Mixing rates. If EV is based on the client fee and AC on internal cost rates, CPI includes your margin and looks healthier than delivery is.

Reading CPI too early. In the first weeks of a project, small numbers swing the ratio. Cumulative CPI becomes more stable once a meaningful share of the work is done.

Example

For example, a consultancy sells a fixed-fee brand identity project for $48,000, built as 300 hours at a $160 blended rate. At the week 5 review, the project lead estimates the work at 60% complete, an EV of 180 hours. The team has logged 225 hours. CPI is 180 / 225 = 0.80. The plan had 70% of the work done by week 5, a PV of 210 hours, which gives an SPI of 180 / 210 = 0.86. If the team continues at this efficiency, the project finishes at 300 / 0.80 = 375 hours, and the extra 75 hours, worth $12,000 at the blended rate, come out of margin.

Related terms

  • Earned value management (EVM)
  • Earned value (EV)
  • Actual cost (AC)
  • Cost variance (CV)
  • Estimate at completion (EAC)
  • Fixed fee project

FAQ

Your business runs better on Pike.

Contact sales
  • ISO 27001 CertifiedISO 27001
  • GDPR CompliantGDPR
  • AICPA SOC 2 Type IISOC 2 Type II

Built to keep sensitive client data secure and private.

Pike box logoPike
Features
ProjectsResourcing & capacityFinance & invoicingDashboardsCustomers & salesTime & absencePike MCPIntegrations
Company
EnterpriseBlogOur storySwitch playbookMigration guideGet in touch
Industries
Creative agenciesMarketing agenciesDigital agenciesConsulting firmsIT consultanciesArchitecture firms
Resources
DocsChangelogPrivacy policyTerms and conditionsGlossaryFree toolsFAQ
All systems operational

Engineered around the 🌎

© 2026 Pike. All rights reserved.