Estimate at completion (EAC)
Estimate at completion (EAC) is the forecast total cost of a project when it finishes, based on cost to date plus the expected cost of the remaining work. Subtracted from the budget behind the fee, EAC gives the forecast overrun or saving, while your team can still change scope, staffing or the client conversation.
EAC formulas and when to use each
PMI defines several ways to calculate EAC. They differ in what your team expects of the remaining work.
Use BAC / CPI when you expect current cost performance to continue. It fits a project that has overrun for reasons that will repeat, such as an underestimated type of work.
Use AC + (BAC - EV) when the overrun came from a one-off event, such as a week lost to a client restructure, and you expect the remaining work to run at the budgeted rate.
Use AC + ETC when the original estimate no longer applies, for example after a scope change or a new technical approach. Your team re-estimates the remaining work from the bottom up.
EAC = BAC / CPI; EAC = AC + (BAC - EV); EAC = AC + ETC
Example: with a BAC of $90,000, an EV of $36,000 and an AC of $45,000 (a CPI of 0.80), the first two formulas give $112,500 and $99,000. The third adds a fresh estimate of the remaining work to $45,000.
Estimate to complete (ETC)
Estimate to complete is the expected cost of the work still to do. EAC covers the whole project; ETC covers only the remaining part.
The most reliable ETC is a bottom-up re-estimate: your project lead lists the outstanding deliverables and the hours each needs. When there is no time for that, derive ETC from the EAC formula you chose. If current performance continues, ETC is the remaining budget divided by CPI. If the remaining work runs at the budgeted rate, ETC is BAC - EV.
ETC = EAC - AC; ETC = (BAC - EV) / CPI
Example: with $54,000 of budgeted work remaining and a CPI of 0.80, ETC is $54,000 / 0.80 = $67,500.
How to read EAC against the budget
Variance at completion (VAC) is the budget minus EAC. A negative VAC is the forecast overrun. On a fixed-fee project it comes straight out of margin. On time and materials work with a cap, it is the amount the client will need to approve or your business will write off.
To-complete performance index (TCPI) is the cost efficiency the remaining work needs to finish on budget: (BAC - EV) / (BAC - AC). A TCPI well above the current CPI means finishing on budget requires a change your team has not yet made.
VAC = BAC - EAC
Example: a $90,000 budget with an EAC of $112,500 gives a VAC of -$22,500.
How agencies and consultancies use EAC
Recalculate EAC at each project review and compare it with the budget the fee was built on. A forecast overrun of 40 hours found in week 4 is a scope or staffing conversation. The same overrun found at handover is a write-off.
Pike tracks hours against project budgets live, in total or per phase, which gives your team current actuals for AC. The estimate of remaining work still comes from the people doing it.
Common mistakes with EAC
Using BAC / CPI by habit. If the overrun came from a one-off, BAC / CPI overstates the final cost. If scope has changed, none of the CPI-based formulas apply and your team needs a bottom-up ETC.
Forecasting from incomplete timesheets. An EAC built on missing time entries is too low by the hours nobody has logged yet.
Treating EAC as a target. EAC is a forecast. If the number is unacceptable, change the plan, then recalculate.
Example
For example, a consultancy sells a $90,000 fixed-fee strategy engagement, budgeted at 600 hours at $150 an hour. Halfway through the schedule, the project lead estimates the work at 40% complete, an EV of $36,000. The team has logged 300 hours, an AC of $45,000, which gives a CPI of 0.80. If the overrun reflects how this work really runs, EAC = $90,000 / 0.80 = $112,500 and ETC = $67,500. If the overrun came from a one-off, EAC = $45,000 + ($90,000 - $36,000) = $99,000. If the team re-estimates 400 hours to finish, ETC is $60,000 and EAC = $45,000 + $60,000 = $105,000. The forecast overrun ranges from $9,000 to $22,500, depending on which view of the remaining work your team trusts.