Margin degradation
Margin degradation is the gradual fall in a project's profit margin between the estimate and final delivery, as costs rise or billable revenue shrinks during the work.
How to measure margin degradation
Compare the margin the project was sold at with its current or final margin. The difference, in percentage points, is the degradation.
Gross margin is a reading at one point in time. Margin degradation is the change between two readings of the same project, so it needs the planned margin recorded at kickoff and the margin recalculated as hours and costs are logged.
Margin Degradation = Planned Margin % - Actual Margin %
Example: a project sold at a 45% margin that finishes at 31% has degraded by 14 percentage points.
What causes margin degradation
Scope creep adds work that the fee does not cover. Unbilled change orders have the same effect: the extra work was agreed with the client and never invoiced.
Over-servicing spends more hours than the budget allowed on work that was in scope. Staffing drift raises cost per hour when a senior person covers tasks priced at a junior rate. Rate card drift raises it across every project when salaries increase and billing rates do not.
How to catch margin degradation early
Track margin while the project is live. A month-end report shows the loss after the hours are spent. Margin recalculated from time entries each week shows the trend while there is still budget to protect.
Compare the share of budget used with the share of work completed. A project that has used 60% of its hours and delivered 40% of its scope is losing margin, even if the total spend is still under budget. That gap is the point to raise a change order, adjust staffing, or reset expectations with the client.
Example
An agency sells a website project for $50,000 and budgets $27,500 of labour cost, a planned margin of 45%. During the build, two extra rounds of revisions add $4,000 of cost, a client request outside the scope adds $1,500 and is not billed, and a senior developer covers work priced at a mid-level rate, adding $1,500. Final cost is $34,500, so the margin is $15,500, or 31%. The project degraded by 14 percentage points. A change order for the out-of-scope request and a limit on revision rounds would have recovered most of it.