Move from monday.com to Pike

Export each monday.com board and its Time Tracking column to Excel, save the files as CSV for the Pike templates, and plan five to six weeks from first export to cutover.

Available now

monday.com exports each board to Excel, one board at a time, so you export every project board on the day you freeze changes and save each file as CSV UTF-8.

  1. 1On each board, open the three-dot menu at the top right and choose More actions → Export board to Excel. The export follows the board’s active filters, so clear filters first.
  2. 2Split any board over 10,000 items with filters before you export. monday.com exports up to 10,000 items at a time.
  3. 3Open the Time Tracking column menu and choose Export Column Data to Excel for item names, the person who tracked time, and totals per item.
  4. 4Save every file as CSV UTF-8 and upload customers, projects, phases, members, tasks, then time entries under Workspace settings → Integrations → CSV, using the monday.com column mapping.

The column export shows time totals per item and person. For one row per session with a date, read the Time Tracking column’s history through the monday.com API.

Available now

monday.com has no invoice record, so your invoice history exists only in the accounting system you bill from. Connect that system to Pike first, then load monday.com boards against its customers.

  1. 1Connect the accounting system your team invoices from under Workspace settings → Integrations and run Import data for customers and invoice history.
  2. 2Copy the customer numbers from that import into the customer column of your monday.com project file, so each board links to a ledger customer.
  3. 3If your team uses the monday.com Pipedrive integration, connect Pipedrive to Pike for organizations, contacts and deals, and leave deal items out of your CSV files.

Pike imports invoice history from the ledger. Pike has no CSV template for invoices.

Entity map

What each monday.com record becomes in Pike

Column one uses monday.com’s labels. monday.com has no client or rate record, so most of the money side of the table is set in Pike from your own records.

Client column or board name

Pike: Customers

Carries over: Whatever your team typed in a client column, or the client name in a board title.

You set in Pike: One customer per billing entity with a customer number. Use the ledger customer list where you connect accounting.

Template columns: customerName, customerNumber

Boards (one per project), or items on a projects board

Pike: Projects

Carries over: Board or item name, Status column, owner in a People column.

You set in Pike: Project number, billing type and hourly rate for every project.

Template columns: projectNumber, title, customerNumber, status, leadEmail

Numbers column used as a budget

Pike: Project budget

Carries over: A money or hours figure, only where your team added a Numbers column for it.

You set in Pike: A budget on every open project without one.

Template columns: budgetAmount, budgetHours

Groups

Pike: Phases

Carries over: Group name on each board.

You set in Pike: Start and end dates.

Template columns: projectNumber, phase

Items and subitems

Pike: Tasks

Carries over: Item name, group, Status column, People column, Timeline or Date column.

You set in Pike: One assignee per row, by email. The People column exports names only.

Template columns: title, projectNumber, phase, status, assigneeEmail, startDate, dueDate

Users (Administration)

Pike: Members

Carries over: Name and email of each user on the account.

You set in Pike: Team, position, workspace role and cost profile.

Template columns: email, displayName

Time Tracking column

Pike: Time entries

Carries over: Sessions per item, each with the user who started it, start and end time. The column export shows totals per item and person.

You set in Pike: Billable status per entry and approval status, which monday.com does not record.

Template columns: date, hours, email, projectNumber, taskTitle, billableStatus

Updates

Pike: Not imported

Carries over: Comments on items. The board export includes item updates and leaves out subitem updates.

You set in Pike: Nothing. Keep the export as your archive.

Invoices

Pike: Invoice history from accounting

Carries over: monday.com has no invoice record. Your invoices exist in the accounting system you bill from.

You set in Pike: Nothing. Pike imports invoice history from the ledger.

monday.com entityPike entityWhat carries overWhat you set in PikeTemplate columns
Client column or board nameCustomersWhatever your team typed in a client column, or the client name in a board title.One customer per billing entity with a customer number. Use the ledger customer list where you connect accounting.customerName, customerNumber
Boards (one per project), or items on a projects boardProjectsBoard or item name, Status column, owner in a People column.Project number, billing type and hourly rate for every project.projectNumber, title, customerNumber, status, leadEmail
Numbers column used as a budgetProject budgetA money or hours figure, only where your team added a Numbers column for it.A budget on every open project without one.budgetAmount, budgetHours
GroupsPhasesGroup name on each board.Start and end dates.projectNumber, phase
Items and subitemsTasksItem name, group, Status column, People column, Timeline or Date column.One assignee per row, by email. The People column exports names only.title, projectNumber, phase, status, assigneeEmail, startDate, dueDate
Users (Administration)MembersName and email of each user on the account.Team, position, workspace role and cost profile.email, displayName
Time Tracking columnTime entriesSessions per item, each with the user who started it, start and end time. The column export shows totals per item and person.Billable status per entry and approval status, which monday.com does not record.date, hours, email, projectNumber, taskTitle, billableStatus
UpdatesNot importedComments on items. The board export includes item updates and leaves out subitem updates.Nothing. Keep the export as your archive.
InvoicesInvoice history from accountingmonday.com has no invoice record. Your invoices exist in the accounting system you bill from.Nothing. Pike imports invoice history from the ledger.

monday.com has no bill rate or cost rate field. Teams that bill from a board add an hourly rate in a Numbers column and multiply it by tracked time in a Formula Column. Use that rate as `hourlyRate` where your boards have one, and set it by hand where they do not.

A budget exists only where your team added a Numbers column for it. Fill `budgetAmount` for money budgets and `budgetHours` for hour budgets, and give every project a `billingType`.

Pike calculates profit from cost profiles, so an admin sets up a cost profile for everyone who tracks billable time before the pilot starts.

The plan

Seven steps out of monday.com

The same steps as the main migration guide, with this tool's screens and settings.

  1. Week 1

    Migration owner, finance

    1

    1Week 1 · Migration owner, finance

    Freeze scope and export

    The board exports are a snapshot. Write down the export date: at cutover you export the time tracked after it.

    • Pick a cutover Friday after the month’s invoices go out from your accounting system.
    • Unarchive every board with open work or billable time from this year. The account export does not include archived boards.
    • Export every project board to Excel and the Time Tracking column of each board, then keep the raw files unchanged in one folder.
    exports / rawdo not edit
    • customers.csvraw
    • projects.csvraw
    • tasks.csvraw
    • time-entries.csvraw
    • invoices.csvraw
    Cutover: Friday, week 5

    Done when: Every board export and Time Tracking export in one dated folder, and a cutover Friday on the calendar.

  2. Week 1 to 2

    Operations lead

    2

    2Week 1 to 2 · Operations lead

    Clean the exported files

    Clean the CSV files, since monday.com boards rarely record client, rate or budget in the same columns.

    • Build one projects file from your boards: a project number, a customer number, a billing type and a budget per row.
    • Replace each People column name with the user’s email from the user list in Administration. Pike matches people by email.
    • Convert tracked time to decimal hours. The API reports session duration in seconds, so divide by 3600.
    customers.csvbefore / after
    • Acme
    • ACME Ltd
    • Acme retainer

    Acme

    C-104 · T&M · 1,250/h

    Done when: Every open project row has a number, a customer number, a billing type and a budget. Every assignee is an email.

  3. Week 2

    Workspace admin

    3

    3Week 2 · Workspace admin

    Build the workspace shell

    Admins set up Pike before the first upload, so they can give imported projects a team and a rate on day one.

    • Create teams and workspace roles. Invite admins and project leads only.
    • Connect your accounting system and run Import data for customers and invoice history.
    • Set a cost profile for everyone who tracks billable time.
    Workspace setup
    • Teams and roles
    • Templates and labels
    • Cost profiles12 of 12
    • Accounting connected
    • Invite everyoneweek 4

    Done when: Finance sees the ledger’s customers and invoices in Pike. Every billable person has a cost profile.

  4. Week 2 to 3

    Workspace admin

    4

    4Week 2 to 3 · Workspace admin

    Upload in dependency order

    Customers, then projects and phases, then members, then tasks and time. Pike reports a row it cannot match with its line number.

    • Download each Pike template and map the board columns with the monday.com column mapping.
    • Upload groups as phases before tasks, so Pike places each item in its phase.
    • Spot check three projects against monday.com: item count, assignees, last month’s tracked hours.
    Import datain order
    • Customers48
    • Projects112
    • Members19
    • Tasks1,430
    • Time entries
    • Deals

    Done when: Board, item, user and last-month hour counts match monday.com.

  5. Week 3 to 4

    Delivery lead, finance

    5

    5Week 3 to 4 · Delivery lead, finance

    One team in Pike for a sprint

    CSV has no ongoing sync, so the pilot team moves fully to Pike while everyone else keeps tracking time in monday.com.

    • The pilot team logs time in Pike only, from Monday. Everyone else tracks time in monday.com until cutover.
    • Finance approves pilot time in Time admin and sends one invoice from Pike.
    • Compare the pilot project’s margin in Pike with the rate and hours from its board. A gap means a rate or cost profile needs a fix in Pike.

    Old tool

    Rest of team

    logs as before

    keep syncing

    Pike

    Pilot team

    approved, invoiced

    Done when: One invoice sent from Pike. No pilot team time in monday.com after the pilot start date.

  6. Week 4 to 5

    Migration owner

    6

    6Week 4 to 5 · Migration owner

    Cutover weekend

    Close monday.com on Friday evening and upload the time tracked since your first export.

    • Friday: everyone stops their timers. Export the Time Tracking column, or read session history through the API, for sessions since your first export and upload those rows.
    • Deactivate users who no longer need monday.com. A user must be deactivated before you can reduce seats.
    • Schedule the seat reduction. monday.com applies it at your next renewal date, and only when active seats are at or below the new number.

    Fri

    Approve. Sync. Read-only.

    Sat, Sun

    Rest.

    Mon

    All in Pike. Demo at 10:00.

    Done when: Time admin shows every active member by Monday afternoon. monday.com shows no tracked time after Friday.

  7. Week 5 to 8

    Finance

    7

    7Week 5 to 8 · Finance

    First month-end in Pike

    Done when finance closes a month without opening monday.com.

    • Approve all time, invoice every billable project from Pike, and check each invoice appears in your accounting system.
    • Write the baseline: days to invoice, unbilled hours at close, margin by project.
    • Run the account export from Administration for the archive, after you unarchive any board you want in it.
    Baselinebefore / Pike
    Days to invoice
    Unbilled hours at close
    Margin by project

    Done when: Month closed in Pike. Final monday.com export saved with two owners. Seat reduction scheduled.

Rebuild

Set these up in Pike by hand

  • Hourly ratesSet the bill rate on each project from the rate column on its board.Pike docs
  • Cost ratesCreate a cost profile per member. monday.com stores no cost rate.Pike docs
  • Workload viewRecreate future assignments as allocations in resource planning.Pike docs
  • Board templatesRebuild your standard board as a Pike project template.Pike docs
  • Status columnsSet task statuses and properties that match your Status column labels.Pike docs

Questions

Moving from monday.com: common questions

Why does our monday.com board export stop short?

monday.com exports up to 10,000 items per board at a time, and the export follows the board’s active filters. Clear filters, then split large boards by filter and export each part.

Does the board export include subitems?

Check whether your export includes subitem rows before you upload. monday.com’s help centre says subitem updates do not export to Excel, only item updates.

How do we get time per day out of the Time Tracking column?

Export Column Data to Excel shows totals per item and per person. For one row per session, read the column’s history through the monday.com API, which records each session’s start, end and user.

Are archived boards in the account export?

No. monday.com’s help centre says archived boards and workdocs are not supported in the account data export. Unarchive the boards you need before you export.

Why does the People column show names and no emails?

The People column records names, and Pike matches people by email. Copy each user’s email from the user list in Administration into the assignee and time files.

Support through the move and after it

Migration support comes with every plan: we map your exports, run the imports with you and check the counts before cutover. After go-live, hypercare until the first month-end closes in Pike. Then we hand over to your admins and stay close for as long as you use Pike. Email hello@usepike.com with your source tool and we will say which route fits.

  • Switch playbook
  • monday.com vs Pike
  • Migration guide for every tool

monday.com documentation used for this guide

  • monday.com: Export from monday to Excel
  • monday.com: How to export your entire account’s data
  • monday.com: The Time Tracking Column
  • monday.com API: Time tracking
  • monday.com API: People
  • monday.com API: Items page
  • monday.com: How to manage users on your account
  • monday.com: Downgrading your plan
  • monday.com: Pipedrive Integration

Your business runs better on Pike.

Contact sales
  • ISO 27001 CertifiedISO 27001
  • GDPR CompliantGDPR
  • AICPA SOC 2 Type IISOC 2 Type II

Built to keep sensitive client data secure and private.

Pike box logoPike
Features
ProjectsResourcing & capacityFinance & invoicingDashboardsCustomers & salesTime & absencePike MCPIntegrations
Company
BlogOur storySwitch playbookMigration guideGet in touch
Industries
Creative agenciesMarketing agenciesDigital agenciesConsulting firmsIT consultanciesArchitecture firms
Resources
DocsChangelogPrivacy policyTerms and conditionsGlossaryFree toolsFAQ
All systems operational

Engineered around the 🌎

© 2026 Pike. All rights reserved.